Governor: Big Dig Bolts Unreliable
Romney says more than 1,400 trouble spots need
reinforcement
BOSTON, Massachusetts (AP) -- Gov. Mitt Romney
said Monday that tests show more than 1,100 bolt
assemblies that used epoxy and more than 300
other areas in a Big Dig connector tunnel where
the ceiling collapsed are unreliable.
Romney, speaking at a Statehouse news conference
where he drew charts and diagrams of the trouble
spots, said all will have to be reinforced.
"In grabbing ahold of these bolts and pulling on
them with excess force, they're letting go ...
at lower pressures than they were designed to
handle," Romney said.
"That suggests that this epoxy system is not
working ... and for that reason we can't count
on it," he said.
Last week, days after 12 tons of ceiling panels
came loose and fell on a car, killing a
passenger, the governor announced that
inspections had found at least 242 points where
bolts were separating from the tunnel roof.
Two Big Dig tunnels have since been closed and
Romney has not yet cleared the way for them to
reopen.
The $14.6 billion Big Dig -- the most expensive
highway project in U.S. history -- buried a
highway network that used to slice through the
city, replacing it with a series of tunnels.
The project also has been plagued by leaks,
falling debris, cost overruns, delays and
problems linked to faulty construction.
Attorney General Tom Reilly, who is considering
filing involuntary manslaughter charges in the
ceiling collapse, said Monday that investigators
had discovered documents showing there was a
"substantial dispute" from 1999 to 2000 over
whether the design of the tunnel was adequate to
hold the weight of the 3-ton ceiling panels.
Reilly, who refused to give specifics, said he
did not know how the dispute was resolved. He
said the tunnel designer, the contractor and the
company overseeing the Big Dig project were
involved but would not say who raised the
questions.
The contractor on the tunnel, Modern Continental
Construction Co., issued a statement saying it
was cooperating with the investigation and is
"confident that our work fully complied with the
plans and specifications provided by the Central
Artery Tunnel Project."
Messages left with project manager
Bechtel/Parsons Brinckerhoff and tunnel designer
Gannett Fleming were not immediately returned.
Commuters on Monday endured increased traffic
hassles with the closing of a second tunnel ramp
connecting two interstates. It was closed Sunday
after testing showed dozens of problems with the
bolts holding up the ceiling. That ramp had been
used as part of a detour around the accident
scene.
Romney said engineers successfully tested a
system to reinforce the bolts.
Romney met earlier in the day with
congressional, state and city leaders to outline
his plan for traffic and to ensure the safe
reopening of the tunnels. After the meeting,
Sens. John Kerry and Edward M. Kennedy endorsed
the governor's plans.
Kennedy said congressional committees are making
plans to hold hearings into the tunnel collapse
and the Big Dig project.
"We want to make sure the issue of safety is
front and center," Kennedy said. |