Workmanship and Design of Tunnel are Called into Question
Problems
with Bolts, Glue Found in Other Tunnel in '98
By Scott
Allen and Sean P. Murphy, Globe Staff | July 12, 2006
Investigators unraveling how concrete ceiling panels
cascaded onto a car in one of the Big Dig tunnels should
focus on some basic, troubling questions about the way the
tunnel ceiling was built, civil engineers and highway
construction specialists said yesterday.
Officials
from the Massachusetts Turnpike Authority suspect that the
accident that killed Milena Del Valle began with the failure
of a single steel hanger that helped hold up the concrete
ceiling, setting off a chain reaction that caused other
hangers to fail and send 12 tons of concrete to the highway
surface as Del Valle's husband drove underneath.
Now,
federal and state investigators are looking into the
possibility that there was some defect in the way the
hangers were manufactured or secured to the roof of the
tunnel connecting the turnpike to the Ted Williams Tunnel. A
1998 report from the state Office of the Inspector General
documented numerous problems with the bolts and glue used to
secure the ceiling in the Ted Williams Tunnel, including the
use of bolts that were too short and trouble with an epoxy
used to glue the bolts into the concrete.
The
inspector general's report was written before construction
of the ceiling section that later collapsed, and it's not
clear whether the same methods were used. However, Governor
Mitt Romney said the report should have served as a warning.
``That
would suggest to a layperson like myself that a very high
degree of care should have been taken in inspecting that
section of the ceiling, and I don't know whether that care
was given or not," said Romney, referring to the I-90
connector tunnel at an afternoon press conference.
The
tunnel section was inspected before it opened to the public
in January 2003 and another inspection was ``in the process"
when the accident happened, Turnpike Authority chairman
Matthew J. Amorello said yesterday. He said turnpike records
from Modern Continental, the company that built the tunnel,
show that the hangers were individually inspected and tested
when completed.
Big Dig
officials say there is no indication of a link between the
ceiling collapse and previous problems such as leaks and use
of inferior concrete.
Civil
engineers said the questions must go beyond the quality of
workmanship to the tunnel's design: Why were the concrete
panels so heavy, weighing 2 1/2 to 3 tons apiece? Why were
they there at all, since there was already a higher tunnel
roof? And why did the failure of a single steel hanger send
six to 10 of the slabs crashing down?
Initial
reports from eyewitnesses and investigators indicate the
accident began with a loud snap as a steel hanger gave way
and the other three holding up a 40-foot steel bar couldn't
handle the extra weight.
``I can't
imagine anybody signing off on a design of suspending 3-ton
concrete panels such that the failure of any one hanger
would lead to 12 tons of concrete coming down on the
highway," said Steve Banzaert , who teaches a course in
``spectacular failures in engineering" at MIT.
A
spokesman for Modern Continental said the company would not
answer specific questions. The company issued a statement
saying it promised to cooperate with the investigation,
while defending its workmanship. ``We are confident that our
work fully complied with the plans and specifications
provided by the Central Artery Tunnel Project," read the
statement, adding that Big Dig officials inspected and
approved the tunnel ceiling.
Bechtel/Parsons Brinckerhoff, the consultant that managed
the design and construction of the project for 20 years,
also promised to work with the Turnpike Authority to
determine the cause.
The
ceiling that collapsed -- inside the eastbound lane of I-90
under South Boston -- is structurally similar to a drop
ceiling, with a lower ceiling suspended from the original
one. However, instead of the light fiber panels used in
homes, the drop ceiling in the Big Dig tunnel is composed of
20-by-40-foot slabs of concrete. The slabs rest on
40-foot-long steel bars that are suspended from the original
concrete ceiling by steel hangers. The hangers are connected
directly to the upper ceiling by a combination of bolts and
glue.
Although
such drop ceilings were built elsewhere in Big Dig tunnels,
a 200-foot stretch where the accident occurred and the Ted
Williams Tunnel have ceilings constructed differently from
those in the rest of the connector and the Interstate 93
tunnel, which were built later, Amorello said. In the I-93
tunnel, a beam with ready-made steel connection points was
embedded inside the concrete when it was poured to make it
easier to suspend the ceiling. But in the affected section,
crews didn't install the drop ceiling until 2000, five years
after the original ceiling was built, forcing them to use
another approach.
``They
used this system of drilling in bolts and bolting it in with
epoxy, and that's what we're investigating," Amorello said.
Michael
P. Lewis , the state Big Dig project manager, said at a
morning press conference that this was ``an approved
method."
``It was
actually the method used in the entire Ted Williams Tunnel,"
he said. ``It's a well-known way of attaching anchors to
concrete structures."
One state
official who has been briefed about the investigation said
one focus is on whether ``a cheaper, quicker" ceiling design
was approved by Big Dig officials for the turnpike section
without adequate consideration of the possible consequences.
The official is not authorized to speak publicly about the
investigation.
This
isn't the first time that investigators have looked at the
quality of Big Dig drop ceilings. In 1998, Inspector General
Robert A. Cerasoli said the project wasted $800,000
attaching hangers to the ceiling of the Ted Williams Tunnel
because designers hadn't foreseen the need to attach hangers
to the original concrete ceiling.
Although
Cerasoli was focused on the needless cost of drilling and
redrilling holes, he said yesterday that he is also
concerned that low-quality work generally could have
compromised tunnel safety. During construction, Cerasoli's
report says, the contractors had trouble with the epoxy --
workers didn't give it time to cure properly or improperly
cleaned holes, and the epoxy's manufacturer suspected the
contractor was not mixing it properly. In a first set of
tests, eight bolts failed out of 50.
Peter Zuk
, the former state Big Dig director, had promised in a
written response to the report to use a better way of
fastening the steel hangers in the future, but the letter
didn't describe the changes, and it was unclear yesterday
whether they happened. However, Modern Continental's
contract was modified several times in 1999, at a cost of
almost $600,000, to allow for changes in the installation of
``adhesive anchors for ceiling struts" in the I-90 tunnel,
according to state records.
``They
really ought to have an independent group come in and
evaluate all of these tunnels," said Cerasoli, inspector
general from 1991 to 2001.
One
construction industry specialist said he questioned whether
the drop ceiling in the turnpike tunnel was needed at all.
Turnpike officials said yesterday that the drop ceiling was
needed to improve the flow of fresh air into the tunnel and
move exhaust fumes out. But the specialist, who is familiar
with the connector tunnel design but asked not to be
identified, said the drop ceiling was there mainly for
aesthetic reasons, to hide fans. He said the section is
vented by open air entrance ramps only about 200 feet away.
Amorello
said engineers will consider reopening the tunnel without
any panels in the section where the accident occurred. He
said that, if ``we can do without it, then we are going to
do without it."
Gareth Cook of the
Globe staff contributed to this report.
|